Ramsey County, in coordination with the City of Lauderdale, is reconstructing Eustis Street between Larpenteur Avenue and the Lauderdale city limits (just north of Como Avenue).

Goals

  • Address pavement issues.
  • Provide continuous sidewalks through the project area.
  • Improve drainage along the corridor. 

Timeline

  • Preliminary Design: 2022-23
  • Final Design and Right of Way: 2024
  • Construction: 2025

Community Engagement

Community open houses were held during the design process to hear from residents. If you missed an open house check out one of the video recaps below.

August 2024 open house

An in-person open house was held on August 7 at Lauderdale City Hall. 

March 2023 open house

An in-person open house was held on March 7 at Lauderdale City Hall. Open house materials are available below.

October 2023 open house

An in-person house was held on Oct. 25 at Lauderdale City Hall. Open house materials are available below.

Project area

Map showing project area along Eustis Street between Larpenteur Avenue and the Lauderdale city limits.